Sunday, 10 January 2010

Week 24 (4 Jan - 8 Jan 2010)



Firstly Happy New Year to all.

Well Christmas and New Year are now over and things started getting back to normal this week, well as normal as you can get in sub zero temperatures!!

A bit of work took place on roof by two very brave roofers! Meanwhile inside the house all the batons have been fixed to ceilings to allow for plaster board fixing (you can see this clearly in pictures below).

I had a site meeting with electrician on Thursday afternoon and we marked out full house for sockets, lights, data points and multiroom audio system. So first fix of electric begins on Friday 8th and hopefully finished by Wednesday 13th.

FAMILY ROOM














FAMILY ROOM WALLS MARKED
















KITCHEN SHOWING BATONS AND WIRES














UTILITY ROOM MARKED OUT FOR SOCKETS & SPURS













CLOAKROOM WHICH WILL HOUSE THE MAINS BOARD

















CAT 5e & SPEAKER CABLE WAITING TO BE INSTALLED